On 6 October 2025, Kavaken flagged a wind turbine whose generator winding temperatures ran above expected values and above similar turbines: Generator Temperature L1 by 13.2% and Generator Temperature L2 by 36.0%. The trend was flat and the risk was rated low. A check of the cooling system found everything within limits, and the flag was closed in March 2026. Kavaken saw the trend still rising and kept the flag under investigation into the summer. The generator later faulted, and the OEM's engineering team concluded that it had to be exchanged. The exchange was reported complete on 25 August 2026.

Within limits is not the same as healthy
Two checks looked at the same generator and reached different conclusions.
Kavaken compares each turbine with its own expected behaviour and with its neighbours in the wind farm. A value can sit inside its limit and still be well above where it should be. In this case, that deviation was the early sign.
323 days, step by step
KavakenSite teamOEMSignal
- Day 0 · 6 Oct 2025 · Kavaken
Kavaken flags generator winding overheating
Generator Temperature L1 and L2 ran 13.2% and 36.0% above expected values and the average of similar turbines. The trend was flat and consistent, and the risk was rated low. The turbine had been above the wind farm average for some time. Kavaken recommended checking the generator winding cooling system, with cleaning or maintenance if needed.
- Day 71 · 16 Dec 2025 · Kavaken
Symptoms also appear in bearing and cooling air
The same anomaly also showed in the front bearing temperature and in the cooling air temperatures.
Flag log, Kavaken (translated): Anomaly symptoms are also visible in front bearing and cooling air temperatures.
- Day 102 · 16 Jan 2026 · Site team
Report sent to the OEM for review
The site team sent a report on the anomaly to the OEM and asked for review and feedback.
Flag log, site team (translated): 16/01: Report sent to the OEM for review and feedback.
- Day 140 · 23 Feb 2026 · OEM
Cooling system check: all within limits
The OEM checked the cooling system. All values were within limits.
Flag log, site team (translated): The OEM will check the cooling system: all within limits.
- Day 157 · 12 Mar 2026 · OEM
Flag closed, OEM engineering informed
The OEM raised the case with its engineering team, and the flag was closed.
- Day 162 · 17 Mar 2026 · Kavaken
Kavaken keeps the flag under investigation
The anomaly trend was still rising. Kavaken moved the flag back under investigation and planned to follow it until the summer, when temperatures peak.
Flag log, Kavaken (translated): The anomaly trend continues to show an upward trajectory. Therefore, it is considered best to keep this flag under investigation until the summer period, when temperatures reach their peak.
- Day 270 · 3 Jul 2026 · Signal
Power limitation starts on the turbine
A power limitation started on the turbine on 3 July 2026. It lasted 1,296.2 hours, with no stop time and an estimated loss of about 7,546 kWh.

Figure 2. A power limitation started on 3 July 2026 and lasted 1,296.2 hours, with no stop time and an estimated loss of about 7,546 kWh. - Day 323 · 25 Aug 2026 · OEM · Fix
Generator faults and is exchanged
The generator faulted. The OEM's engineering team concluded that a generator exchange was required. The exchange was carried out and reported complete on 25 August 2026, and the flag was resolved.
Flag log, site team (translated): Generator faulted on the 13th. The OEM's engineering concluded that a generator exchange would be required. The exchange commenced on the 12th and was completed on the 19th.
Why it stayed hidden
Nothing crossed a limit. The cooling system check found all values within limits, the trend was flat and consistent, and the risk was rated low. The deviation was not new: the turbine had run above the wind farm average for some time. It only stood out when the turbine was compared with its own expected values and with similar turbines.
The outcome
The early warning was proved right. After the flag was closed in March 2026, Kavaken kept it under investigation because the trend was still rising. The generator later faulted. The OEM's engineering team concluded that a generator exchange was required, and the exchange was reported complete on 25 August 2026.
This was not a prevented failure: the generator faulted before it was exchanged. The client rated Kavaken's role as helpful.
- Production
- 240 MWh
- Financial
- USD 23,900
- CO2
- 50 t
Avoided-loss potential: Kavaken's estimate of the loss that the early finding prevented. It is not a realized saving.
Takeaway
Inside the limits is not the same as healthy. When a turbine runs well above its own expected values and its neighbours for months, keep the flag open and follow the trend into the hottest season.