Customer stories / Generator windings / Failure risk

    Within limits, 36% above expected: a generator that later faulted

    Generator winding temperatures ran 13.2% and 36.0% above expected values, with a flat trend and a low risk rating. A cooling system check found everything within limits, and the flag was closed. Kavaken kept watching the rising trend. The generator later faulted and was exchanged.

    Wind240MWhavoided-loss potential
    +13.2%
    Generator Temperature L1 above expected
    +36.0%
    Generator Temperature L2 above expected
    323 days
    from flag to resolution
    1,296.2 h
    power limitation from 3 July 2026

    On 6 October 2025, Kavaken flagged a wind turbine whose generator winding temperatures ran above expected values and above similar turbines: Generator Temperature L1 by 13.2% and Generator Temperature L2 by 36.0%. The trend was flat and the risk was rated low. A check of the cooling system found everything within limits, and the flag was closed in March 2026. Kavaken saw the trend still rising and kept the flag under investigation into the summer. The generator later faulted, and the OEM's engineering team concluded that it had to be exchanged. The exchange was reported complete on 25 August 2026.

    Line chart of generator coolant outlet temperature with a flag marker in early October 2025 and many red out-of-range points through spring and summer 2026, next to a scatter plot of temperature against grid current.
    Figure 1. Generator coolant outlet temperature from 45 days before the flag onward, against its expected band. Red points mark readings outside the expected range, from autumn 2025 into summer 2026.

    Within limits is not the same as healthy

    Two checks looked at the same generator and reached different conclusions.

    Cooling system check
    Within limits
    The OEM checked the cooling system and found all values within limits. The flag was closed on 12 March 2026.
    Kavaken comparison
    +36.0%
    Generator Temperature L2 ran 36.0% above expected values and above the average of similar turbines. Generator Temperature L1 ran 13.2% above.

    Kavaken compares each turbine with its own expected behaviour and with its neighbours in the wind farm. A value can sit inside its limit and still be well above where it should be. In this case, that deviation was the early sign.

    323 days, step by step

    KavakenSite teamOEMSignal

    1. Day 0 · 6 Oct 2025 · Kavaken

      Kavaken flags generator winding overheating

      Generator Temperature L1 and L2 ran 13.2% and 36.0% above expected values and the average of similar turbines. The trend was flat and consistent, and the risk was rated low. The turbine had been above the wind farm average for some time. Kavaken recommended checking the generator winding cooling system, with cleaning or maintenance if needed.

    2. Day 71 · 16 Dec 2025 · Kavaken

      Symptoms also appear in bearing and cooling air

      The same anomaly also showed in the front bearing temperature and in the cooling air temperatures.

      Flag log, Kavaken (translated): Anomaly symptoms are also visible in front bearing and cooling air temperatures.

    3. Day 102 · 16 Jan 2026 · Site team

      Report sent to the OEM for review

      The site team sent a report on the anomaly to the OEM and asked for review and feedback.

      Flag log, site team (translated): 16/01: Report sent to the OEM for review and feedback.

    4. Day 140 · 23 Feb 2026 · OEM

      Cooling system check: all within limits

      The OEM checked the cooling system. All values were within limits.

      Flag log, site team (translated): The OEM will check the cooling system: all within limits.

    5. Day 157 · 12 Mar 2026 · OEM

      Flag closed, OEM engineering informed

      The OEM raised the case with its engineering team, and the flag was closed.

    6. Day 162 · 17 Mar 2026 · Kavaken

      Kavaken keeps the flag under investigation

      The anomaly trend was still rising. Kavaken moved the flag back under investigation and planned to follow it until the summer, when temperatures peak.

      Flag log, Kavaken (translated): The anomaly trend continues to show an upward trajectory. Therefore, it is considered best to keep this flag under investigation until the summer period, when temperatures reach their peak.

    7. Day 270 · 3 Jul 2026 · Signal

      Power limitation starts on the turbine

      A power limitation started on the turbine on 3 July 2026. It lasted 1,296.2 hours, with no stop time and an estimated loss of about 7,546 kWh.

      Event summary showing 0 min stop time, 0 kWh stop loss, 1,296.2 h limitation time and 7,546 kWh limitation loss for a power limitation starting 3 July 2026.
      Figure 2. A power limitation started on 3 July 2026 and lasted 1,296.2 hours, with no stop time and an estimated loss of about 7,546 kWh.
    8. Day 323 · 25 Aug 2026 · OEM · Fix

      Generator faults and is exchanged

      The generator faulted. The OEM's engineering team concluded that a generator exchange was required. The exchange was carried out and reported complete on 25 August 2026, and the flag was resolved.

      Flag log, site team (translated): Generator faulted on the 13th. The OEM's engineering concluded that a generator exchange would be required. The exchange commenced on the 12th and was completed on the 19th.

    Why it stayed hidden

    Within limits
    cooling system check result
    Low
    risk rating, with a flat trend

    Nothing crossed a limit. The cooling system check found all values within limits, the trend was flat and consistent, and the risk was rated low. The deviation was not new: the turbine had run above the wind farm average for some time. It only stood out when the turbine was compared with its own expected values and with similar turbines.

    The outcome

    The early warning was proved right. After the flag was closed in March 2026, Kavaken kept it under investigation because the trend was still rising. The generator later faulted. The OEM's engineering team concluded that a generator exchange was required, and the exchange was reported complete on 25 August 2026.

    This was not a prevented failure: the generator faulted before it was exchanged. The client rated Kavaken's role as helpful.

    Production
    240 MWh
    Financial
    USD 23,900
    CO2
    50 t

    Avoided-loss potential: Kavaken's estimate of the loss that the early finding prevented. It is not a realized saving.

    Takeaway

    Inside the limits is not the same as healthy. When a turbine runs well above its own expected values and its neighbours for months, keep the flag open and follow the trend into the hottest season.

    Next caseA new main bearing reset its history, but not its gap to the fleetRead the case →
    Kavaken

    Autonomous Asset Performance Managementfor Renewable Energy

    Monthly updates from Kavaken. Unsubscribe anytime.

    United Kingdom

    Kavaken Limited

    TUSPark Eagle Labs
    27 Grainger Street
    Newcastle, NE1 5JE

    United States

    Kavaken, Inc.

    2500 Yale St Ste B
    Houston, TX 77008

    Türkiye

    Kavaken Yazılım A.Ş.

    Resitpasa Mah. Katar Cad.
    ITU ARI 8, 2/11
    Istanbul, 34467

    Member of:
    ORE CatapultNOFGWECTÜREBAmerican Clean Power
    Find us at:
    LinkedInYouTube

    © 2026 Kavaken. All rights reserved.