Customer stories / Generator bearing (NDE) / Failure risk

    A climb made on a low-risk flag found a bearing that needed cleaning

    A generator bearing ran 37.7% warmer than similar turbines in the same wind farm. With a low risk rating, it was easy to leave for later. The service team climbed the turbine because of the Kavaken flag, found a cleaning need, and the anomaly faded after a bearing oil check and cleaning.

    Wind290MWhavoided-loss potential
    +37.7%
    above similar turbines
    Day 33
    bearing oil check and cleaning
    131 days
    flag to resolution

    On 1 October 2025, Kavaken flagged the non-drive-end bearing of a wind turbine generator. It was running 37.7% warmer than the average of similar turbines in the same wind farm, with a consistent deviation and a rising trend. The risk was rated low, so nothing forced a visit. The OEM service team climbed the turbine on 3 November 2025 because of the flag, found a cleaning need, and carried out a bearing oil check and cleaning. Signs of the anomaly began to fade around 8 December. The flag was resolved on 9 February 2026.

    Line chart of generator non-drive-end bearing temperature from August 2025 with a shaded band, highlighted points and a dashed flag line in October 2025, next to a scatter of the temperature against generator rotational speed.
    Figure 1. Generator non-drive-end bearing temperature against a shaded band, starting 45 days before the flag. The dashed line marks the flag on 1 October 2025.

    What Kavaken pointed to

    Kavaken named insufficient lubrication as the most likely root cause. It pointed to blockages in the bearing lubrication system chimneys and to accumulations in the waste oil reservoir.

    The recommendation was to clean these areas first. A check of the automatic lubrication mechanism was also recommended, with maintenance if needed.

    131 days, step by step

    KavakenOEMSignalSite team

    1. Day 0 · 1 Oct 2025 · Kavaken

      Kavaken flags a warm generator bearing

      The generator non-drive-end bearing temperature was running 37.7% above the average of similar turbines in the wind farm. The deviation was consistent, the trend was rising, and the risk was rated low. Kavaken recommended cleaning the bearing lubrication discharge and checking the automatic lubrication.

    2. Day 31 · 1 Nov 2025 · OEM

      Inspection visit scheduled

      The OEM service team planned to climb the turbine two days later to inspect the bearing.

      Flag log, site team (translated): The OEM service team will go up the turbine on 3 November 2025 to inspect it.

    3. Day 33 · 3 Nov 2025 · OEM · Fix

      Bearing oil checked and cleaned

      The OEM service team carried out an oil check and cleaning of the generator bearing.

      Flag log, site team (translated): Generator bearing oil check and cleaning were carried out.

    4. Day 68 · 8 Dec 2025 · Signal

      The anomaly starts to fade

      Around 8 December, the bearing temperature showed signs that the anomaly was disappearing.

    5. Day 110 · 19 Jan 2026 · Site team

      Site confirms the flag drove the visit

      The site confirmed that the intervention was made because of the Kavaken flag, and that a cleaning need was found on the turbine. The anomaly symptoms appeared to be gone.

      Flag log, site team (translated): Site comment: the intervention was made on the Kavaken flag. When the turbine was climbed, a need for cleaning was seen.

    6. Day 131 · 9 Feb 2026 · OEM

      Flag closed as resolved

      The flag was closed as resolved, with the cleaning by the OEM service team recorded as the fix.

      Flag log, site team (translated): The OEM service teams carried out the cleaning and the problem was solved.

    Why it stayed hidden

    +37.7%
    against similar turbines in the same farm
    Low
    risk rating at the flag

    The bearing temperature stood out when it was compared with similar turbines in the same wind farm. The deviation was steady rather than sudden, and the risk was rated low. Nothing pushed the issue up the work list until the Kavaken flag led the service team to climb the turbine and look.

    The outcome

    After the bearing oil check and cleaning on 3 November 2025, signs that the anomaly was disappearing appeared around 8 December. On 19 January 2026 the site reported that the anomaly symptoms appeared to be gone. The flag was resolved on 9 February 2026.

    The site confirmed that the intervention was made because of the Kavaken flag, and that a cleaning need was seen on the turbine. The client rated Kavaken's role as helpful.

    Production
    290 MWh
    Financial
    USD 18,600
    CO2
    180 t

    Avoided-loss potential: Kavaken's estimate of the loss that the early finding prevented. It is not a realized saving.

    Takeaway

    A steady temperature deviation against similar turbines can be worth a climb even when the risk is rated low. Here a bearing oil check and cleaning, done on the flag, was followed by the anomaly fading about five weeks later.

    Next caseNo SCADA warning, yet the generator NDE bearing ran 15.5% too warmRead the case →
    Kavaken

    Autonomous Asset Performance Managementfor Renewable Energy

    Monthly updates from Kavaken. Unsubscribe anytime.

    United Kingdom

    Kavaken Limited

    TUSPark Eagle Labs
    27 Grainger Street
    Newcastle, NE1 5JE

    United States

    Kavaken, Inc.

    2500 Yale St Ste B
    Houston, TX 77008

    Türkiye

    Kavaken Yazılım A.Ş.

    Resitpasa Mah. Katar Cad.
    ITU ARI 8, 2/11
    Istanbul, 34467

    Member of:
    ORE CatapultNOFGWECTÜREBAmerican Clean Power
    Find us at:
    LinkedInYouTube

    © 2026 Kavaken. All rights reserved.