Kavaken flagged the main shaft bearing of a wind turbine when its temperature ran 8.8% above the expected range and 14.7% above the average of similar turbines on the site. The divergence had started in late July and was progressing quickly. The first SCADA high-temperature warning on this bearing came in November 2025. Four days after the flag was raised, the site team found an oil leak at the main bearing. They relubricated it, took an oil sample and planned a borescope inspection. The temperature divergence continued in the following months. The client closed the flag on 31 August 2026 and reported that the main bearing had been replaced.

376 days, step by step
KavakenSite teamSignal
- Day 0 · 20 Aug 2025 · Kavaken
Kavaken flags main bearing heat
Kavaken's models detected anomalous heat behaviour in the main shaft bearing. The flag was raised on 21 August 2025. The bearing temperature was 8.8% above its expected range and 14.7% above the average of similar turbines on the site. The deviation was consistent and on a rapidly rising trend.
Flag log, Kavaken (translated): The main bearing temperature indicator is running 8.8% above the expected range and 14.7% above the average of similar turbines at the site. The divergence from the expected range and from the other turbines began towards the end of July and progressed quickly.
- Day 5 · 25 Aug 2025 · Site team · Fix
Oil leak found, bearing relubricated
The site team found an oil leak at the main bearing and relubricated it. They took an oil sample and planned a borescope inspection.
Flag log, site team (translated): Oil leak detected. Lubrication done. Oil sample taken. Borescope planned.
- Day 36 · 25 Sep 2025 · Kavaken
Anomaly progresses, flag risk raised
The anomaly calculated by the sensor models for the rotor bearing temperature signal DTR RotBearTemp 1 kept progressing. Kavaken raised the flag to risk level 2. On 30 October 2025 the divergence from the other turbines on the site was still present.
- Day 90 · 18 Nov 2025 · Signal
First SCADA high-temperature warning
SCADA raised its first DTR RotBearTemp 1 high-temperature warning on the bearing, lasting 38.1 hours. A second warning followed on 23 November 2025 and lasted 10.4 hours. Neither stopped the turbine.

Figure 2. SCADA events of the flag, November 2025 to June 2026: high-temperature warnings on the bearing and low-level warnings on the rotor bearing container, all with 0 kWh loss. - Day 141 · 8 Jan 2026 · Site team
Check planned at scheduled maintenance
On 7 January 2026 Kavaken noted that the divergence was continuing and asked for a status update. The next day the site team replied that the bearing would be checked during the Type-3 maintenance.
Flag log, site team (translated): A check will be made during the Type-3 maintenance. Estimated date of the maintenance work: January 2026 – February 2026.
- Day 230 · 7 Apr 2026 · Signal
Bearing container low-level warnings begin
SCADA raised low-level warnings on the rotor bearing container on 7, 8 and 10 April 2026. On 6 May 2026 the same warning started again and lasted 135.4 hours.
- Day 321 · 7 Jul 2026 · Kavaken
Kavaken asks about flushing or replacement
The divergence and the anomaly were still present. In June and early July 2026, SCADA raised seven high-temperature warnings on the bearing. Kavaken asked whether a flushing or a replacement was being planned.
Flag log, Kavaken (translated): The divergence and the anomaly continue. If a flushing or a replacement is planned, we ask for the details to be entered.
- Day 344 · 30 Jul 2026 · Signal
Longest warning and a short limitation
A DTR RotBearTemp 1 high-temperature warning started and lasted 185.2 hours, the longest of the flag. It triggered a 6-minute power limitation with an estimated loss of 5.8 kWh. Further warnings followed on 8 August (115.0 hours) and 16 August 2026.

Figure 3. SCADA events of the flag, July to August 2026, including the 185.2-hour high-temperature warning and the 6-minute power limitation of about 6 kWh. - Day 376 · 31 Aug 2026 · Site team
Main bearing replaced, flag resolved
The client reported that the main bearing had been replaced, and the flag was resolved.
Flag log, site team (translated): The main bearing has been replaced.
Why it stayed hidden
At the flag, the bearing temperature was moderately above its expected range, with a consistent deviation. The first SCADA high-temperature warning on the bearing came three months later. None of the warnings that followed stopped the turbine. The only production effect was a 6-minute power limitation in July 2026, with an estimated loss of 5.8 kWh. The deviation showed in the comparison with the expected range and with similar turbines on the site, not in alarms that forced action.
The outcome
The client reported on 31 August 2026 that the main bearing had been replaced, and the flag was resolved.
The relubrication in August 2025 did not end the anomaly. Kavaken recorded continued divergence from the site turbines in October 2025, January 2026 and July 2026. SCADA high-temperature warnings on the bearing recurred from November 2025 to August 2026. Low-level warnings on the rotor bearing container appeared in April, May and August 2026. In the product chart, no anomaly points are marked on the bearing temperature after August 2026.
The client rated Kavaken's role as helpful.
- Production
- 630 MWh
- Financial
- USD 47,600
- CO2
- 390 t
Avoided-loss potential: Kavaken's estimate of the loss that the early finding prevented. It is not a realized saving.
Takeaway
A main bearing that drifts away from its expected range and from similar turbines is worth a physical check before any alarm, and here it led straight to an oil leak. When relubrication does not bring the temperature back, keep tracking the divergence and plan the larger work.