Customer stories / Gearbox bearing (NRE) / Failure risk

    Low-risk gearbox bearing flag, gearbox replaced within about a month

    Kavaken flagged anomalous heat behavior at the gearbox non-rotor-end bearing. The flag was rated low risk, and the trend was flat rather than climbing. The site team replaced the gearbox with a repaired unit in January 2024, and the bearing returned to normal.

    Wind400MWhavoided-loss potential
    Low
    risk rating at the flag
    21 days
    flag to replacement plan
    ~1 month
    flag to gearbox replacement
    2 stops
    for gearbox work, January 2024

    On 6 December 2023 Kavaken flagged anomalous heat characteristics at the gearbox non-rotor-end bearing of a client's wind turbine. The flag was rated low risk, with a straight trend: the bearing was behaving out of character, but no value was climbing towards a limit. Three weeks later the site team was planning a gearbox replacement. In early January 2024, after stops for gearbox filtration work and gearbox work, the turbine received a repaired gearbox. After the replacement the bearing's behavior returned to normal.

    Two charts. Left: gearbox non-rotor-end bearing temperature over time with red anomaly markers and a data gap. Right: the same temperature plotted against rotor speed from 0 to 14 RPM, rising gently, with one outlier near 325 °C at 0 RPM.
    Figure 1. Gearbox non-rotor-end bearing temperature (HSS) in the Kavaken product, over time and against rotor speed: across 609 paired days the temperature rises with rotor speed, with one isolated high reading at standstill.

    Flag to gearbox replacement in about a month

    KavakenSite team

    1. Day 0 · 6 Dec 2023 · Kavaken

      Bearing heat behavior flagged

      Kavaken flags anomalous behavior in the heat characteristics of the gearbox non-rotor-end bearing. The indicator is overheating, the risk is rated low and the trend is straight.

    2. Day 21 · 27 Dec 2023 · Site team

      Gearbox replacement planned

      The site team reports that a gearbox replacement is being planned.

      Flag log, site team (translated): Site comment: A gearbox replacement is being planned.

    3. Day 26 · 1 Jan 2024 · Site team · Fix 1 of 2

      Stop for gearbox filtration work

      The turbine is stopped for gearbox filtration work, part of the replacement work on the gearbox.

    4. Day 41 · 16 Jan 2024 · Site team · Fix 2 of 2

      Gearbox replaced with a repaired unit

      A second stop is logged for gearbox work. In early January 2024 the turbine's gearbox was replaced with another gearbox that had been repaired on 4 January 2024.

      Flag log, site team (translated): The turbine's gearbox was replaced with another gearbox that had been repaired on 4 January 2024.

    5. 26 Nov 2025 · Site team

      Back to normal after the replacement

      The site team confirms that the bearing behavior returned to normal after the gearbox replacement. The flag was closed on this date as an administrative step, long after the work was done in January 2024.

      Flag log, site team (translated): Returned to normal after the gearbox replacement.

    Why it stayed hidden

    Low
    risk rating
    Straight
    trend, no steady climb

    The anomaly was in how the bearing heated, not in a value racing upwards. With a straight trend and a low risk rating, nothing was escalating towards a limit that would force a stop. The signal was a change in the bearing's heat characteristics, which shows up when its temperature is read against the turbine's operating conditions.

    The outcome

    The site team confirmed that the bearing behavior returned to normal after the gearbox was replaced with a repaired unit in early January 2024.

    The client rated Kavaken's role as helpful.

    The flag stayed open in the system until 26 November 2025 and was then closed as an administrative step. The work itself was done about a month after the flag.

    Production
    400 MWh
    Financial
    USD 37,200
    CO2
    260 t

    Avoided-loss potential: Kavaken's estimate of the loss that the early finding prevented. It is not a realized saving.

    Takeaway

    A low-risk rating with a flat trend can still point at a gearbox worth acting on. When bearing heat behavior changes against operating conditions, planning the gearbox work early lets it happen in a short, controlled window.

    Next caseTransformer windings ran 30% hot while the air around them cooledRead the case →
    Kavaken

    Autonomous Asset Performance Managementfor Renewable Energy

    Monthly updates from Kavaken. Unsubscribe anytime.

    United Kingdom

    Kavaken Limited

    TUSPark Eagle Labs
    27 Grainger Street
    Newcastle, NE1 5JE

    United States

    Kavaken, Inc.

    2500 Yale St Ste B
    Houston, TX 77008

    Türkiye

    Kavaken Yazılım A.Ş.

    Resitpasa Mah. Katar Cad.
    ITU ARI 8, 2/11
    Istanbul, 34467

    Member of:
    ORE CatapultNOFGWECTÜREBAmerican Clean Power
    Find us at:
    LinkedInYouTube

    © 2026 Kavaken. All rights reserved.